| Callaway
SGR |
|
|
63
Day World Record Outage |
|
|
Primary
Pipe Welds - zero weld defects |
|
|
Zero
OSHA Recordables |
|
|
16
REM under dose goal |
|
|
Total
Scope completed under budget |
| |
|
Salem-1
RVCH & IHA Installation
|
|
|
25 Day World Record Outage |
|
|
Zero
OSHA Recordables |
|
|
Zero
Radiological Overexposures |
|
|
Zero
Schedule Impact to RFO Duration (Stretch Goal 336
Stand to Stand - Actual 310 hours) |
|
|
Zero
Rework |
|
|
Zero FME Events |
|
|
Zero
Human Performance Issues |
|
|
Zero
Operational Start-up Issues |
| |
|
| ANO-1
RVCH & ESS Installation |
|
|
ESS
Delivered and Installed without significant issues |
| |
|
| ANO-1
SGR |
|
|
World
record installation for OTSG with a RVCH and polar
crane upgrade (78 days) |
|
|
FOAK
application of narrow Groove single-sided ferritic
clad weld with zero weld defects |
|
|
Primary
Pipe Welds - zero weld defects |
|
|
Total
Scope completed under budget and ten days ahead
of schedule |
| |
|
| PSL-1
Pressurizer Replacement |
|
|
FOAK
In Industry Installation - On Schedule |
|
|
No
weld defects on Surge Line Weld |
| |
|
| PSL-1
RVCH Installation & Shroud Upgrade |
|
|
FOAK
CEDM Welding completed 1-week ahead of schedule
with no weld defects |
| |
|
| PSL-1
Hot Leg RTD Repairs |
|
|
Completed
two shifts ahead of schedule |
| |
|
| TMI-1
A600 Repair on Pressurizer & HPI T/S Replacement |
|
|
Contributed
to shortest outage in TMI-1 history |